Stormwater Upgrade Stage 4

Stormwater Upgrade Stage 4

  • Company: Orica Chemnet
  • Location: Mount Maunganui, New Zealand
  • Date: August 2012 - August 2013
+ Overview

Contract Mechanical Services were engaged by Orica Chemnet to do the Mechanical and Piping installation for their Stormwater Stage 4 upgrade.

This consisted of:

  • installing 2 x 120,000 litre Stormwater Storage Tanks
  • installation of associated pumps, pipeworks and feeds to the system from various positions on site
  • design, construction and installation of inground collection points
  • installation of sump grating
  • fabrication and installation of safe walkways around the new areas.
= Outcome

CMS completed all scheduled work - and additional unforeseen work - with no impact or downtime on the existing effluent handling system.

Our post contract evaluation was Excellant.

 

CMS Project Supervisor
Brian Dally, Gareth Lilley

Project Manager
Marie Grimshaw - Orica ESS